The project consists of the construction of a new Sewer Lift Station including abandonment and removal of the existing Sewer Lift Station located in Schertz, TX. The work includes the installation of 3,700 LF of 48” FRP pipe and manholes, and the decommissioning of the existing 27” and 15” Sewer lines. The work involves boring of 66” steel sasing under the UPR Railroad Track and FM78, trenching to an average depth of 24’, sewer bypassing 24 Hrs. a day while installing the new FRP Pipe. Additionally, the project will include site grading, concrete flatwork, electrical, site restoration, and site fencing.
Client:
CIBOLO CREEK MUNICIPAL AUTHORITY (CCMA)
Start Date:
February 2024
End Date:
August 2025
Contract Amount:
$13 MILLION