Overview
The initial implementation of a detour and utilization of a temporary bridge opens up the project for the construction of the main interchange. This project is a 3-bridge interchange that will be completed in multiple phases due to the need for demolition of existing bridges and new bridge construction, along with horizontal and vertical roadway improvements.
Client:
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION
Start Date:
January 2024
End Date:
March 2028
Contract Amount:
$42 MILLION