Overview

On April, 3 2020, Zachry Construction Corporation completed the Texas Department of Transportation's (TxDOT) new parking lot for the Fort Worth district headquarters. The completetion came a month  ahead of schedule despite several change orders.


Far from a simple parking lot, the work entailed placing four 500-foot-long box culverts under the lot top maintain flow  from a drainage creek thath runs through the property. After placing seven feet of fill over the culverts, the team prepared  a new subgrade and laid five and a half inches of asphalt, as well as concrete curb and gutter. They also included a new storage space for TxDOT's maintenance equipment.

Client:

TEXAS DEPARTMENT OF TRANSPORTATION

Start Date:

September 2019

End Date:

April 2020

Contract Amount:

$3.7 MILLION